Skip to content

Retaining Wall & Erosion Protection – Platipus® Civil Anchors

Facebook
LinkedIn
Twitter
WhatsApp

Project Details

Contractor

Crosana Pty Ltd

Client

N/A

Engineer

Sheehy & Partners Consulting Engineers

Location

Tweed River, NSW

Project Information

The project involved providing further stability and erosion control to an existing 12m long x 2m high retaining wall adjacent to a private property on the River Tweed in NSW.

Design

The consultant designed a 2m high anchor tie-back shotcrete (Natracliff style finish) retaining wall. Two levels of Platipus B4 Anchor Systems were installed at 2m centres along the 12m length of wall. The passive ‘Design’ Loads of the anchor systems were 20kN (2t).

Installation

Twenty Platipus B4 Anchor Systems were installed to depths of 3m by mechanical means and utilising a hand-held jack hammer. Each Anchor System was tensioned, load locked and tested to a ‘30kN’ Proof Load. The vertical wall face was finished with a Natracliff style shotcrete.

The Platipus anchoring systems were chosen and deployed for the following main features & benefits:

  • Mechanical installation using a hand-held jack hammer for a difficult access project site
  • All Platipus B4 anchor systems were installed and instantly load verified in two days
  • Environmental contamination to the adjacent river course and surrounding area was minimised by designing and installing ‘dry’ mechanical earth anchor systems, no grouting measures necessary!
  • A Natracliff style shotcrete proving a more natural looking wall face

Products used in this Project